Building for Our Family of Faith

.

Continuing Projects

  1. Church — The first foundation pour for the new parish center began on Friday, August 13, and is ongoing as it will take 5–6 pours to lay.
  2. Kearsage Parking Lot — The lot will be available beginning this weekend (August 15–16) for parking. The Kearsage Street sidewalk will be the only route to the Church.
  3. School — Finishing work is being done this week in the Science Room/Resource Classroom. We anticipate completion by the first week of school.

Adoration Chapel Parking in School Lot

We hope, sometime this week adorers will be able to use the new Kearsage Street parking lot. Until then, please follow previous parking plan (school lot).

Please remember…

  • Pedestrian Walkways — For your safety, do not bypass the safety fences around the construction areas.
  • Rectory Entrance — Please access the parish offices by ringing the bell at the door on the north side of the rectory garage. The Rectory offices open at 9:00 a.m. during this phase of construction.

Thank you for your continued patience and understanding with the detours and inconveniences during our building project. All these disruptions will have been worth it once we have our new facilities. If you have any questions, please contact Deacon Tony at the Rectory.

 