Building for Our Family of Faith

.

Continuing Projects

  1. Church — The first foundation pour for the new parish center began on Friday, August 13, and is ongoing. The foundation is 75% completed.
  2. Kearsage Parking Lot — Open and ready for use.
  3. School — The Science Room/Resource Classroom is completed and operational.
  4. Electrical Utility Work — Ongoing throughout the project. Power will be shut down at the school on Tuesday, August 31.

Adoration Chapel

A new wood chip sidewalk leading from the new Kearsage St. parking lot along the north side of the Convent building to the entrance of the chapel is in place and operational.

Please remember…

  • Pedestrian Walkways — For your safety, do not bypass the safety fences around the construction areas and please watch your step.
  • Rectory Entrance — Please access the parish offices via the new Kearsage St. parking lot and ring the bell at the door on the north side of the rectory garage. This is the only entrance to the Rectory and business office. Do not try to use the front door. The Rectory offices open at 9:00 A.M. during this phase of construction.

Thank you for your continued patience and understanding with the detours and inconveniences during our building project. All these disruptions will have been worth it once we have our new facilities. If you have any questions, please contact Deacon Tony at the Rectory.

 